Managing Steading Drainage and Rural Sustainable Drainage Systems
This is an old version of the page
This is an old version of the page
Date published: 30 March, 2015
Date superseded: 5 January, 2016
The aim of this item is to improve water quality by helping to minimise the volume of dirty water and slurry produced, and to treat surface water run-off from clean or lightly contaminated surfaces, prior to discharge to the water environment.
This item will fund works such as:
- the installation of underground pipework to convey drainage from a collection point to where it will be discharged, such as to a slurry collection facility or to a rural sustainable drainage system
- concreting existing uncovered steading or court surfaces to minimise the contamination of clean run-off
- re-grading existing concrete areas to change the direction of run-off
- the installation of ramps / sleeping policemen and / or channels or kerbs to help keep clean and dirty water separate
Rural sustainable drainage systems, such as wetlands, ponds, swales and retention ponds, can then be used to treat the drainage collected from clean or lightly contaminated areas.
Many rural sustainable drainage systems features can also offer potential biodiversity and landscape benefits.
Eligibility
The steading must be within a diffuse pollution priority catchment or focus area, unless an endorsement has been obtained from the Scottish Environment Protection Agency.
You must combine this option with at least one of the following associated capital items:
Spatial targeting
You can check if this item is available on your holding here.
Application requirements
You must prepare a steading drainage plan which must include a map of the steading, identifying clean and dirty yard areas, and the actions that will be taken to improve drainage management.
Requirements
Lightly contaminated run-off collected via works funded under this option must not drain directly to a watercourse.
Payment
You can claim:
Standard cost items
- underground drainage (including surface fittings, underground pipe, fittings, access chambers) – £54 per linear metre
- concreting existing uncovered steading or court surfaces) – £57 per square metre
- surface drainage interception:
- re-grade existing concrete areas – £65 per square metre
- installation of ramps / sleeping policemen – £120 per square metre
Actual cost items
To ensure value for money, we require you to provide three competitive quotes for the installation of kerbs / channels / cross drains.
This can include:
- purchase and installation of proprietary shallow-surface drainage channels, including cover lid or grate
- purchase and installation of proprietary kerbs
- installation and formation of kerb or channels from concrete in situ
Inspections
The inspectors will check:
- the linear length of drainage (including surface fittings, underground pipe, fittings and access chambers)
- the area of any concreting of existing uncovered steading or court surfaces
- the area of any surface drainage interception
- that lightly contaminated run-off collected via works does not drain directly to a watercourse